Entries in natural gas (35)

Monday
Dec052016

2016/2017 winter outlook: sufficient electricity supplies expected

Natural gas pipeline constraints remain a concern, Winter Reliability Program implemented

Electricity supplies should be sufficient to meet New England’s consumer demand for electricity this winter, but possible natural gas pipeline constraints could limit electricity production from natural gas power plants. A Winter Reliability Program has been implemented to incentivize gas and oil-fired power plants to procure sufficient fuel before winter begins. View the press release.

Click to read more ...

Monday
Aug222016

Requests to participate in 2016/2017 Winter Reliability Program due October 1

 

Market participants: Requests to participate in the Oil Program, LNG Program, or Demand Response Program are due to ISO New England Customer Service by October 1, 2016. 

Read FERC approves reliability program for winters 2015/2016, 2016/2017, and 2017/2018 to learn more about the Winter Reliability Program and why the ISO is implementing these programs for the coming three winters.

See the Winter Program Payment Rate page for details on payment rates.

Click to read more ...

Monday
Jan042016

Update on the 2015/2016 Winter Reliability Program

9/9/16 update: The chart has been updated with final program participation results. Despite “the winter that wasn’t” (read the winter 2015/2016 operations recap), the winter reliability program remains instrumental in augmenting New England’s fuel security.

In September, the Federal Energy Regulatory Commission approved a program for the current and next two winters to address seasonal reliability challenges created by constraints on New England’s interstate natural gas pipeline system. The previous programs for winters 2013/2014 and 2014/2015 proved to be cost-effective short-term solutions to help keep the lights on in New England during very cold winter days.

Click to read more ...

Tuesday
Oct132015

ISO New England's response to Pilgrim Nuclear Power Station retirement request

On Monday October 12, 2015, Entergy Nuclear Power Marketing submitted to ISO New England a formal request to retire its Pilgrim Nuclear Power Station by June 1, 2019. Pilgrim, a 680-megawatt (MW) electric generating plant located in Plymouth, Massachusetts, is among the region’s largest power plants and is one of three remaining nuclear stations in New England. Entergy’s 620-MW Vermont Yankee Nuclear power plant retired in December 2014. In 2014, nuclear power generated 34% of the electricity produced in New England. Read the press release.

Click to read more ...

Tuesday
Sep292015

ISO-NE invited to share research and experiences at influential 2015 IEEE Power & Energy Society General Meeting

ISO engineers make strong showing, receive accolades on research related to new technologies for “Powering Up the Next Generation”

As in past years, several ISO New England power system engineers were asked to share their expertise, findings, and business-case experience at the 2015 IEEE Power & Energy Society General Meeting in July. The Power & Energy Society (PES) is a highly regarded international association for leaders in the field of electric power engineering and is part of the Institute of Electrical and Electronics Engineers (IEEE)—the world's largest professional association dedicated to advancing technological innovation and excellence. Through their participation in the PES, ISO employees help expand the knowledge base and advance the industry.

Click to read more ...

Thursday
Sep172015

FERC approves reliability program for winters 2015/2016, 2016/2017, and 2017/2018

Proposal selected is nearly identical to last year’s program

On July 15, 2015, ISO New England and the New England Power Pool (NEPOOL) filed alternative Winter Reliability Program (WRP) proposals with the Federal Energy Regulatory Commission (FERC) to address the region’s well-documented reliability challenges over the next three winters.

Click to read more ...